Problem 1.
253
90%
| 253 LCY/hr |
|---|
Problem 2.
296 LCY;
228 BCY
| 228 BCY/hr |
|---|
Problem 3.
Lasers and TV cameras are used to verify aligment and boring depth.
Problem 4.
FF=0.95; BL=0.95 cy; E=0.8
109
| 109 cy/hr |
|---|
Problem 5.
17950-604-298=17048
| 17,048 lb |
|---|
Problem 6.
W=10000+1200=11200 → R≤180'
| 180' |
|---|
Problem 7.
C: 160 cyc/hr;
S:
1.17;
V: 0.75 cy;
B: 0.80;
E: 0.7;
TAF: 0.95;
LF=0.77;
AT=30/36 * 5/3 = 1.4 sy
74.7 LCY/hr
57.5 BCY/hr
123 ft/hr
| 123 ft/hr |
|---|
Problem 8.
C: 160 cyc/hr; S: 1.08; V: 1.5 cy; B: 0.90; E: 50/60; LF=0.80;
194.4 LCY/hr
155.5 BCY/hr
| 55.5 BCY/hr |
|---|
Problem 9.
Shovels remove material using a frontal or parallel appbroach.