Problem 4-1.
1.15
| 1.15 |
|---|
Problem 4-2.
0.3738
| 37% |
|---|
Problem 4-3.
Problem 4-4.
Problem 4-5.
14.75 ≈ 15 days
Expected delivery date is 15 days from order date. To expect it one day earlier, order one day earlier.
Problem 4-6.
Power Shovel Production:
685.7 BCY/day = 720 LCY/day
Dump Truck Cycle Time:
0.025 day
Dump Truck Production:
320 LCY/day
Three trucks are needed.
Problem 4-7.
377.91
| 378 yd³/day |
|---|
76.19
| 76 sec |
|---|
Problem 4-8.
0.036765 day
217.6
| 218 yd³/day |
|---|
1.824
| 2 trucks |
|---|
Problem 4-9.
a.
720 yd³
b.
1515 sec;
142.6 yd³
5.454 → 6 trucks
c.
411 yd³;
105 sec
d.
71.3 yd³;
6.2 → 7 trucks


Discussion